How to review a quantity takeoff before you bid

A takeoff is only as good as the drawings behind it. These are the checks we run before pricing a single line item.

Before measuring anything, confirm which revision of the plans you are working from and whether any addenda change the scope. A takeoff built on superseded drawings produces a number that looks complete and is wrong.

Start with the drawing revision

Write the revision and date at the top of the report. When a question comes up later, the team can tell immediately whether the quantity reflects the current design.

Check units and waste factors

Concrete is ordered in cubic yards, block in units, framing in linear feet and drywall in square feet. Mixing units inside one report is the fastest way to a bid that is off by an order of magnitude.

  • Confirm that the unit on every line matches the way the material is bought.
  • Apply waste factors to materials that get cut: tile, flooring, rebar and lumber.
  • Separate quantities that include formwork, reinforcement and pumping from the concrete volume itself.

Spot-check the largest items

Measure three or four of the biggest line items again from the drawings. If they match the report, you can trust the rest. If they do not, stop and find the reason before pricing anything.